FPSO Cuulong MV9 External Turret
Scope of Work
SOFEC designed and constructed an external turret mooring system to moor the 149,500 dwt MODEC purpose-built FPSO. The FPSO receives produced oil and reinjects both produced gas and water. The SOFEC turret is designed to support a single production platform in Phase I, with space to accept additional production from a second future production platform in Phase II of the project.
General Description
Client Name: | CUU Long Joint Operating Company (CLJOC) |
Contract Award: | May 2002 |
Installation Date: | October 2003 |
First Oil: | October 2003 |
Vessel Size: | 149,500 dwt |
Storage Capacity: | 1,000,000 bbls |
Water Depth: | 48m (157ft) |
Fabrication: | Turret - Malayasia Vessel - Korea Topsides - Korea |
Design Environmental Criteria
(100-year storm)
Significant Wave Height: | 8.0m (26.2ft) |
Wind Velocity: | 28m/s (54.4 knots) |
Surface Current: | 1.4m/s (2.7 knots) |
Mooring System
Turrets
9-leg 3 x 3 chain catenary mooring
External Cantilevered Bow
Fluid Swivel Assembly
Oil / Water: | 1 x 12-in. toroid (1,480 psi design) |
Gas Lift: | 1 x 8-in. toroid (2,220 psi design) |
Gas Production: | 1 x 10-in. toroid (2,220 psi design) |
Water Injection: | 1 x 12-in. toroid (3,705 psi design) |
Spare: | 1 x 12-in. toroid (3,705 psi design) |
Future Gas Production Swivels: | 2 x 12-in. toroid (2,220 psi design) |
Riser System
3 x 11-in. Flexible riser
1 x 7-in. Flexible riser
2 – Electrical control umbilicals
Comments
First oil was achieved 18 months after contract award. The SOFEC external turret mooring system is ABS classed.